Exterior walls going up at Westonka Library
Weekly progress at Westonka Library continues to be robust. Crews have been working simultaneously inside and outside, building out the envelope (exterior), framing walls, and roughing in mechanical, electrical, and plumbing. With drilling of the geothermal wells starting recently, the site will be exceptionally busy and crowded in the coming weeks.
Exterior wall coverings (sheathing) are nearly complete, with vapor barrier installation following behind. This view shows the fully formed porch-canopy wall openings.
The curved shade element along the park porch is framed and nearly fully sheathed. To the right, the main reading room’s north wall is framed. Sub-slab ductwork along the outer perimeter was placed in June and is already backfilled. The concrete floor will be poured later this month.
South porch, looking west from the outside corner of the multipurpose room.
Paving in front of the staff entrance has been poured.
Interior-partition framing is underway in the back-of-house area, which includes the staff work and break rooms, restrooms, wellness, and the mechanical areas.
Equipment pads in the mechanical room were also recently poured.Upcoming Work
Work scheduled for the rest of July focuses on:
- Drilling of the geothermal wells
- Setting floor boxes
- Pouring slab-on-grade floor by end of month
- Sheeting and insulation of sloped roof
- Installing exterior air-barriers and finishes
Project updates
Interested in receiving future updates on the project? Subscribe to the Westonka Library email list or visit the Westonka Library building project page.
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends