Scaffolding installed, interior ceiling work to begin at Southdale Library
A maze of scaffolding has been installed in the new Southdale Library atrium. In the coming months, all high ceiling work across the structure will be completed. Crews will use this temporary scaffolding platform to access the ceiling to install remaining mechanical, electrical, and plumbing work.
In recent weeks:
- Building mockup passed water and air testing
- Surface parking lot and paver installation was completed
- South half of site has been seeded and sprouts are popping
Progress photos
Viewing northwest from the future plaza
New parking lot and paver work complete
Wall framing/mechanical, electrical, and plumbing installation continues
Timber clean up and final sealing has begun
Various stakeholder and partner groups tour the siteUpcoming work
- Enclosing building by winter
- Entry canopies, timber refinishing, and elevator/stairwells
- Mechanical room equipment build out
- Mechanical, sprinkler, and electrical piping, and infrastructure work
- North parking lot and sidewalks