Concrete pours for first-level slab at Southdale Library have begun
Despite January’s bitter cold temperatures, the Southdale Library project is moving ahead with noteworthy progress since the last update.
Recent project highlights include:
- Drilling for two geothermal wells is complete at a depth of around 455 feet each
- System work will continue this spring
- Heat from geothermal pumps will provide heat to the finished building
- The footings, including column piers, are complete
- First-level slab form and rebar placed
- Concrete pours for first-level slab have begun
Aerial view of the Southdale Library new build site.
Forms in place.
Forms in place.
Project team reviews the progress.
Project team reviews the progress.
Columns in lower level.
Columns in lower level.
Another aerial view of the Southdale Library new build site.Project updates
Another aerial view of the Southdale Library new build site.Project updates
Interested in receiving future updates on the project? Subscribe to the Southdale Library email list or visit the Southdale Library building project page.