Cedar Avenue safety improvements
We are working to make it safer and easier to travel on Cedar Avenue (County Road 152) between Lake and 42nd streets in South Minneapolis. In coordination with the City of Minneapolis, we plan to reconstruct the road from spring 2028 through fall 2029.
We are working to make it safer and easier to travel on Cedar Avenue (County Road 152) between Lake and 42nd streets in South Minneapolis. In coordination with the City of Minneapolis, we plan to reconstruct the road from spring 2028 through fall 2029.
-
Fall 2025 public engagement summary
Public engagement for the first stage of the safety improvement project took place throughout Fall 2025. The engagement team collected community feedback in the following ways: hosted an open house, walk and bike audits, created an online survey, business canvassing and conversations with those riding the bus.
Participation by the numbers
- Open house: 45 attendees
- Walk and bike audits: 12 participants
- Online survey: 136 submissions
- Business canvassing: 49 businesses visited
- Conversations with people riding the bus: 12 conversations
What we heard
- Community members expressed a strong desire for physical infrastructure (raised crosswalks, concrete bump outs, etc.) to increase pedestrian safety
- Community members want walk and bike improvements to be prioritized as much as car improvements
- Community members want Cedar Avenue to be more welcoming to encourage people to access local businesses
Improvement priorities
At the open house and on the online survey, participants were asked to choose their top three priorities for Cedar Avenue. Here are the combined results:
- Traffic calming – 121
- Safer crosswalks – 106
- Green space and tree canopy – 65
- Improving the surface of the road – 54
- Improving and connecting sidewalks – 47
- Maintaining the amount of on-street parking – 44
- Increased lighting – 36
- Bus stop improvements – 33
- Aesthetic improvements to the corridor - 19
Follow Project
Who's Listening
-
ES
Phone 612-596-0569 Email emily.schulz@hennepin.us -
PB
Phone 612-673-2460 Email peter.bennett@minneapolismn.gov
Project timeline
-
August 2025
Cedar Avenue safety improvements has finished this stageProject kick-off
-
Fall 2025 - Summer 2026
Cedar Avenue safety improvements is currently at this stagePreliminary design and engagement
-
Winter 2026 - Winter 2027
this is an upcoming stage for Cedar Avenue safety improvementsFinal design
-
Spring 2028 - Fall 2029
this is an upcoming stage for Cedar Avenue safety improvementsConstruction